Wird diese Nachricht nicht richtig dargestellt, klicken Sie bitte hier.
load images
load images
load images

meet the grs-team at the windenergy in hamburg

Global Renewables Shipbrokers GmbH welcomes all visitors to booth B4.EG.318 - HALL B4 at the leading international WindEnergy Hamburg exhibition in September.
The GRS shipbroker team will be ready to answer all questions and discuss any topics concerning:

  • Offshore Tonnage for Charter
  • Offshore Tonnage for Sale & Purchase
  • Offshore Equipment
  • Cargo Runs
  • Research and Consulting
We are looking forward to seeing  you there!
load images

VesselS FOR charter

load images
Jack Up´s
Starting Day Charter Rate
unpropelled: 26.000 EUR
DP<500t crane: 32.000 EUR
DP>500t crane: 35.000 EUR
load images
WALK-2-WORK
Starting Day Charter Rate
<40 ChrtsPax: 19.000 EUR
>40 ChrtsPax: 24.000 EUR
load images
Construction Vessel
Starting Day Charter Rate
DP2<50t gear: 15.000 EUR
DP2>100t gear: 22.000 EUR
more vessels
load images

VesselS FOR SALE

load images
TUG (#432)
Built:
LoA:
Beam:
1975
38,15 m
9,20 m


Speed: 13 kn
Draft:
BP:
Crane:
3,83 m
50 tons
65 mt

Price: EUR      800.000,-
load images
CTV (#427)
Built: 2012
LoA: 28,10 m
Beam: 8,50 m
Crane:
Pax:
Speed:


1mt @7,28
12
29 kn
Price: GBP        1.600.000,-
load images
OSV (#195)
Built: 1977
LoA: 78,87 m
Beam: 15,21 m
Speed: 12 kn
Acc.:
Deck Space:
Crane:
DP1
Price: USD
36
548 sqm
5mt @ 14m

1.000.000
more vessels
load images

Join our Next cargo runs

load images

OFFSHORE VESSELS


load images


apollo



Croatian shipbuilder Uljanik Shipyard has delivered the multipurpose, selfpropelled jack-up vessel Apollo to GeoSea. Apollo is the first self-propelled platform built in Uljanik. The Apollo platform is based on the GustoMSC NG-5500X design. The jack-up is equipped with four 106.8 metres long legs that allow it to work at depths of down to 70 metres. With a deadweight of 5,196.2 tonnes, the vessel is 89.32m long, 42m wide, 8m high and is able to reach a speed of 11.92 knots powered by the main engines: 4 x ABC 2,688kW and 2 x ABC 1,512kW.Apollo offers standard accommodation for 90 people, and is intended for various operations on all seas of the world, such as wind turbine installation, heavy load transportation and assembly, and can also be used as an accommodation platform. The vessel will sail under the Luxembourg flag and will be one of Uljanik’s key references in the world for building complex, highly sophisticated ships, the shipbuilder said.


load images

Atlantic amsterdam



Under the contract secured in March, the UK-based company is in charge of providing accommodation and construction support for the hookup and commissioning of the project’s offshore substation, which was installed in June. The duration of the project is 60 days, with the possibility of extending the charter period for up to 120 days, Ørsted said. HSM Offshore is the EPC contractor for the substation, while Heerema Marine Contractors was responsible for the transport and installation of the topside, jacket and piles. Borkum Riffgrund 2 will comprise 56 MHI Vestas 8MW turbines located next to Borkum Riffgrund 1 some 57km off the north-west coast of Germany. The 450MW project recently generated its first power to the German grid, while full commissioning is scheduled for 2019.


load images


Edda mistral



The Service Operation Vessel (SOV) Edda Mistral has left the Ria del Eo, Spain, to head towards the Port of Gijón where the vessel will complete her sea trials over the next weeks. Built by Spain’s Gondan for the Norwegian shipowner Østensjø Rederi A / S, Edda Mistral will operate on Ørsted’s Hornsea Project One wind farm in the UK. Her sister vessel, Edda Passat, also built by Gondan for Østensjø Rederi, is deployed on Ørsted’s Race Bank wind farm in the UK. Both vessels have contracts for a fixed period of five years, plus five one-year options. With 81m in length and a 17m beam, the vessels have the capacity to accommodate a crew of up to 20 people and up to 40 technicians who will perform maintenance tasks at the wind farms. Both vessels are equipped with a 23-meter-long Uptime heave compensated walk-to-work gangway, a 3D compensated crane and a CTV landing system with bunkering facility. In addition to the gangway, the vessels are equipped with a Helideck and an 11m daughter craft.

load images

OFFSHORE WINDParks

load images

ORSTED GETS SET FOR HORNSEA FOUR SURVEYS

Orsted plan to embark on a sediment sampling campaign for the Hornsea Project Four offshore wind farm next month. The company has applied to the UK Marine Management Organization for a marine license to take up to 30 samples during a geotechnical campaign due to commence on the 11th September until 31st December. A vessel will deploy either a mini-Hamon or day grab sampler to take cores of less than 1m3 within the prescoping boundary of the array and export cable corridor. The Hornsea Four offshore area is 860km2, and has a potential capacity of 3.6GW. Orsted are currently considering the number and size of turbines and their locations so that it can develop its consenting strategy. The cable route is likely to be 100-120 km with 20-30km of onshore cable to the substation at Cottingham. Orsted has begun stakeholder engagement and has appointed Environmental Consultants and a legal team to help progress with a consent application.
load images

guangdong celebrates first wind farm

The first offshore wind project in the Guangdong Province, the Zhuhai Guishan Demonstration project, was fully commissioned on the 14th August. Third Harbour Engineering Co., Ltd. undertook construction work with the last turbine installed on the on 14th May 2018. The project features 34 Mingyang and United Power (SCD 3MW and UP3000-108 3MW) turbines with total capacity of 120MW and represents an investment of ¥4450m (€568.75m). Over the past couple of months 13 projects under development in the Guangdong province have been picking up the pace. The Zhuhai Jinwan project has received approval from the Zhuhai Development and Reform Commission, turbine installation is underway at the Yudean Zhanjiang Wailuo windfarm and tenders are being held for survey and design work for the Huaneng Lemen 2 project. Earlier this year the Guangdong province announced an ambitious offshore wind development plan for the development of 23 projects with a total planned capacity of 66.85GW accounting for around 50% of China’s total planned capacity.
load images

Vineyard wind achieves record low price 

It has been announced that the first large-scale US offshore wind farm, the 800MW Vineyard Wind project, will deliver electricity at $65/MWh (€56/MWh). This is $100/MWh below the predicted maximum and significantly lower than the 30 MW Block Island project in Rhode Island which signed a PPA of $244/MWh. Vineyard Wind and the Massachusetts’ Electric Distribution Companies concluded long-term contract negotiations last week stating that the project will save consumers 1.5% on their monthly energy bills. The contracts will be delivered in two phases with the first 400MW phase coming online in 2022 and the second 400MW phase in 2023. Vineyard Wind has begun supply chain investigations and recently participated in its first series of ‘meet the buyer’ events. The developer is also working on drafting a supplement to the Environmental Impact Report which was submitted to the state in April and BOEM are expected to release the Draft Environmental Impact Statement this autumn.

load images

Vattenfall says goodbye to utgrunden

Dismantling of Vattenfall’s oldest wind farm, Utgrunden, will be completed by the end of August. The 10.5MW project was built in 2000 and acquired by Vattenfall from Ørsted in 2006. Located in Kalmarsund, it features seven Enron Wind 70/1500 1.5MW turbines and 11km of subsea cabling. Vattenfall decided against repowering the project explaining that the turbines are of extremely low power compared to current models. For example, the Enron turbine has a rotor diameter of 70m whilst the new MHI Vestas V164-9.5 MW model has a 164m rotor diameter. According to Vattenfall the site is too small to accommodate turbines of such scale and it would be too expensive to modernize the plant. The Utgrunden turbines were disconnected on the 14th June and WIND PIONEER arrived on site in mid-July to begin the multimillion dismantling process. The monopile foundations and cables are also due to be completely removed by the end of the month.
load images

South korea to build first floating turbine

Ulsan City plan begin construction of South Korea’s first floating offshore wind turbine this year with installation during H1 2019. The 750kW UNISON 750/U57 turbine will be 46m long and 80m high. It will be located off the coast of Seogyeonmyeon, Ulsansi where average wind speeds are 8.5m/s and water depths are at least 40m. The aim of the project is to demonstrate the feasibility of the technology prior to the potential deployment of a 200MW floating offshore windfarm. South Korea is new to the offshore wind market but has ambition. The country’s first commercial scale offshore wind farm, the 30MW Tamra project, was commissioned last year and the country has a potential 3GW of capacity in the pipeline. Swedish multiturbine platform designer Hexicon AB recently signed a Memorandum of Understanding (MoU) with Busan Techno Park and Renewable Energy Center for the development of floating offshore wind in South Korea.
load images

over halfway at the rentel wind
farm

Turbine installation at the 309MW Rentel offshore wind farm is steaming ahead. According to Otary, the majority owner of the project, 28 of the 42 SWT-7.0-154 turbines have been installed and are all exporting power to the grid. The turbines have a nominal capacity of 7MW which can be boosted to 7.35MW under the correct conditions. Each blade is 75m long with a tip height of 196m above LAT making them the tallest offshore wind turbines in Belgium. The total weight of the rotor, nacelle and tower is 950 tons, which is equivalent to 75 double-decker buses. DEME’s installation vessel Sea Installer is currently operating out of Ostend and all the turbines are expected to be in the field and operational before end of summer. Otary is also developing the Seamade (Seastar and Mermaid) sites representing a total capacity of over 800MW to be constructed in Belgium over the next two years.

load images

OFFSHORE News

load images

Kvaerner and innogy dispute still ongoing

Norwegian engineering and construction company, Kvaerner and Innogy are still butting heads regarding the dispute over the supply of jackets for the Nordsee Ost offshore wind farm, located 35km off the coast of Helgoland. Kvaerner were contracted to manufacture and deliver 48 jacket foundations in June 2010 for €75million. Installation of the first jacket commenced in October 2012, the last jackets were delivered in October 2013 and foundation installation finished in March 2014. The dispute arose when Kvaerner asked for compensation for additional costs and change in scope of work. In 2012, arbitration was filed by Kvaerner against Innogy. Still ongoing six years later, Kvaerner has stated that the ‘arbitration process for the project will take time due to high complexity’ and that ‘it is currently still not possible to estimate when the arbitration will be finalized or the expected financial outcome’. 
load images

Hammer time for new noise reducing tech

New noise reducing pile hammer technology has been successfully tested off the coast of the Netherlands by the Carbon Trust, Fistuca and multiple industry partners. The BLUE 25M hammer utilizes a large water tank to provide a more energetic, but quieter blow. It is designed to reduce underwater noise levels by up to 20 dB and is predicted to reduce the fatigue damage during installation of piles by up to 90%. Van Oord’s HLV Svanen tested the hammer on 13th August within the Borssele wind farm zone. Noise pollution from offshore wind farm construction is a hot topic at the moment. The UK Department of Business, Energy and Industrial Strategy (BEIS) is currently undertaking a review of consents for offshore wind farms within an area of the North Sea to be designated for the protection of harbour porpoises. This review could see consents being altered or revoked. BEIS is due to publish a Habitats Regulations Assessment this summer and will assess the potential noise pollution from selected wind farms.
load images

MHI Vestas gets the green light

The MHI Vestas has received certification for the world’s most powerful commercially available wind turbine, the V164-9.5 MW. The turbine has received S class type verification marking a significant step towards double-digit MW turbines. As the latest version of MHI Vestas’ V164 platform the 9.5MW model has 80m long blades and a 164m rotor diameter. Equipped with a Rotor-Nacelle-Assembly Component Certificate MHI Vestas now aims to begin installations in late 2019. Several projects have already lined up to install the 9.5MW giant including Northwester 2 (224MW), Borssele 3&4 (731.5MW), Borssele V (20MW), Triton Knoll (860MW) and Moray East (950MW) totalling nearly 300 turbines. According to 4C analysts, MHI Vestas is the second leading turbine supplier in Europe with a 16% market share. The company also recently announced its readiness to compete in the first round of offshore wind projects in Taiwan, signing five MOUs and a 9MW turbine platform will be typhoon ready by 2020. The company also announced today that it has joined the Global Wind Energy Council (GWEC) ‘to help open up markets for offshore wind around the world'.
load images

GRS Global Renewables Shipbrokers GmbH – Stadthausbrücke 7 – 20355 Hamburg – Managing Partner: Philippe Schönefeld, Matthias Mroß – Court of Registry: Hamburg – Commercial Registry: HRB 119000 – VAT-ID: DE278136733

T.: +49 40 411 60 68 0 / F.: +49 40 411 60 68 99

E.: info@grs-offshore.com / W.: www.grs-offshore.com